EPZ

EPZ Borssele implemented a new control system during plant shutdown of summer 2017. The project was part of the lifetime extension program of the nuclear facility in Borssele.

ECC solutions executed the project completion management based on workpacks and managed the punch items for construction and pre-commissioning phase.

Notified bodies complemented ECC Solutions with there working methods and the handover results.

Service: Commissioning
Industry: Nucleair
Client: EPZ 
Location: Borssele
Year/Period: Oktober 2016 – Juni 2017

Total Refinery

The OPTARA project, involved the installation of a new solvent de-asphalting unit and a mild hydrocracking unit at the refinery to convert heavy fuel oil into desulphurised diesel and ultra-low, sulphur heating oil. The existing atmospheric residue desulphurisation unit was also being upgraded as part of the project. ECC Solutions executed on behalf of Actemium Netherlands the complete coordination and execution of the loopchecking. During start-up ECC Solutions delivered start-up assistance.

Service: Commissioning
Industry: Oil
Client: Total Refinary 
Location: Antwerp -Belgium
Year/Period: 2015 - 2017

Damen Offshore & Conversions

Implementation of a Mechanical Completion management system including all standard forms to be used during construction, pre-commissioning phase also procedures for standarization on the project. QA/QC: Auditing,discuss ITP's and to make a standard of procedures. The multi disciplinair inspection team of ECC Solutions has executed all inspections for the project. ECC Solutions also provided a document management system including team.

Client: Damen Offshore & Conversions
Location: Schiedam - The Netherlands
Year/Period: 2015 - 2017

BP Norge / Heerema Fabrication Group

Fabrication and Integration contract by BP Norge of the largest offshore topside, including flare boom structure, ever built in the Netherlands. This Intregated Production & Hotel facility of the Valhall Re-Development project will replace the two existing PCP and LQ platforms.

Service: Commissioning
Industry: Oil
Client: BP Norge / Heerema Fabrication Group
Location: Zwijndrecht - The Netherlands
Year/Period: March 2008 - September 2010

ECC Solutions B.V.
Driehoekstraat 29
4706 NC Roosendaal

 P.O. Box 5011 | 4780 KA Moerdijk

 +31 88 80 81 600
info@eccsolutions.nl

 Follow all our vacancies and news on our socials

Contact

If you are interested in more information regarding our services, please fill out the following form. We will get back to you as soon as possible.